    Expo 2020’s iconic Al Wasl dome crowned in groundbreaking engineering feat

    Lifting the final section of Al Wasl dome into place marks a significant milestone in Expo 2020 delivery

    Raising more than 800 tonnes of steel hundreds of feet into the air with a margin of error of three millimetres – that was the complex and intricate task to complete the iconic dome structure of Expo 2020’s central Al Wasl Plaza.

    The crowning is a key milestone in Expo 2020’s delivery and the result of months of meticulous planning, with the final piece of the 130-metre-wide, 67.5-metre-tall dome positioned with the aid of special lifting equipment. More than 800 engineers and construction experts and technicians worked on the groundbreaking feat, using GPS indicators to ensure perfect alignment.

    Comprising 550 tonnes of moulded steel, Al Wasl dome’s crown was precisely positioned using a technique called ‘strand-jacking’: 18 hydraulic jacks, aided by steel lifting ropes connected to 18 freestanding temporary columns, slowly raise the curved steel crown into place. Including the structures and equipment required to lift the dome during this process, the total weight was 830 tonnes.

    Al Wasl dome encloses a space of 724,000 cubic metres – the volume of almost 300 Olympic-size swimming pools – and stands taller than the Leaning Tower of Pisa. It uses 13.6 kilometres of steel, the equivalent of the height of 16 Burj Khalifas; weighs 2,544 tonnes, the same as 25 blue whales; and is almost as wide as two Airbus A380 aircraft lined up wing to wing.

    The crowning is the culmination of more than 14 months of preparation that began when the final pieces of the dome’s steel trellising left Italy on 26 June 2018. Now positioned, the final piece of Al Wasl dome will be welded to the rest of the trellis, a process that will take 25 days.

    Expo 2020’s Official Programme Delivery Management Provider, Jacobs Mace, worked on the overall project management and companies from the United States, Canada, China, France, Japan and Mexico also played key roles in the completion of the dome.

    The name Al Wasl means ‘connection’ in Arabic, and Al Wasl Plaza will be the beating heart of the Expo 2020 site, connecting the three Thematic Districts and providing a focal point for visitors throughout the six-month event. Al Wasl Plaza, which includes the dome’s unique structure, was designed by U.S.-based Adrian Smith + Gordon Gill Architecture.

    The crowning of Al Wasl dome is the latest milestone in Expo 2020’s fast-developing site, with all permanent Expo-led construction on track to be completed by the end of 2019.
    • 21 1月 2020
      世博新闻
      书法主题长凳环绕整个 2020 年世博会场地,营造灵动诗意空间

      著名建筑师阿西夫·汗携手卓富创意的阿拉伯印刷设计师拉拉·卡普坦,将众包文字转化为精致艺术品

      阅读更多
    • 21 1月 2020
      世博新闻
      2020 年迪拜世博会的大门:通往另一新奇世界的门户

      由著名建筑师阿西夫·汗设计的 2020 年世博会入口采用超现实主义风格,独具特色

      阅读更多
    • 15 1月 2020
      世博新闻
      Dulsco 计划推出该地区首创的环保巴士,推动循环回收工作

      2020 年世博会旨在通过其废物管理合作伙伴 Dulsco 组织的全国巴士巡游,提高公众对智能回收重要性的认识

      阅读更多
    • 30 12月 2019
      世博新闻
      百事公司与 2020 年世博会为百万游客推出联名产品

      首批 2020 年世博会冠名百事系列产品将在中东、北非和亚洲地区发售

      阅读更多